NRC to Review WCS Application, Announces Hearing Opportunity And Meetings on Scope of Environmental Review?

Nuclear Regulatory Commission – Press Release
No: 17-004 January 26, 2017
Contact: Maureen Conley, 301-415-8200

The Nuclear Regulatory Commission has docketed and accepted for formal review an application from Waste Control Specialists to build and operate a spent nuclear fuel consolidated interim storage facility in Andrews, Texas. The NRC’s decision follows an acceptance review to determine whether the application contains sufficient information for the agency to begin its formal review.

WCS is seeking to store 5,000 metric tons uranium of spent fuel received from commercial nuclear power reactors across the United States.

The agency’s review will proceed on two parallel tracks – one on safety issues, the other on environmental issues. Both the safety and environmental reviews must be completed before the NRC makes a final licensing decision on the application.

The NRC’s Jan. 26 letter to WCS sets a schedule for its safety and environmental reviews, with a target of making a licensing decision by the third quarter of fiscal year 2019, assuming WCS provides high-quality responses, on schedule, to any NRC requests for additional information. The public will have 60 days from publication of a notice of docketing in the Federal Register, which will appear shortly, to submit requests for a hearing and petition to intervene in the licensing proceeding for the proposed facility. Details on how to submit those requests and petitions will be in the Federal Register notice.

The NRC will accept public comments on the scope of its Environmental Impact Statement through March 13. Details on how to submit those comments will be published shortly in the Federal Register and can be found below.

The NRC will hold two public meetings near the site of the proposed facility to take public comments on the scope of the environmental review. The meetings will be held

  • 7-10 p.m. Mountain Time, Feb. 13, at the Lea County Event Center, 5101 N. Lovington Highway, in Hobbs, N.M.
  • 7-10 p.m. Central Time, Feb. 15, at the James Roberts Center, 855 TX-176, in Andrews, Texas.

Anyone interested in attending or speaking is encouraged to pre-register by calling 301-415-6957 no later than three days prior to the meeting. The public may also register in person at each meeting. The time allowed for each speaker may be limited, depending on the number of registered speakers.

The NRC is also planning to hold additional scoping meetings at agency headquarters in Rockville, Md., during the week following the local meetings. Details are being finalized. Anyone interested in attending should check the NRC public meeting schedule for the dates and times.

Written comments on the EIS scope should refer to Docket ID NRC-2016-0231. Comments will be made publicly available and should not include identifying or personal information you do not wish to be disclosed. Comments can be filed via the federal rulemaking website; or by mail to Cindy Bladey, Office of Administration, Mail Stop: OWFN-12 H08, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.

Feds sue to block acquisition of Dallas radioactive waste company

The U.S. Justice Department is suing to block the acquisition of Dallas-based Waste Control Specialists, which wants to expand the nuclear waste dump it operates in West Texas.

NOV. 18, 2016

By Kiah Collier
Texas Tribune

WCS storage site
An overhead view in 2012 of Waste Control Specialists’ low-level radioactive waste storage facilities near Andrews, Texas. Photo: David Bowser

The U.S. Justice Department is suing to block a Salt Lake City-based company’s acquisition of Waste Control Specialists, the Dallas-based company that wants to expand the nuclear waste dump it operates in West Texas.

If the $367 million merger with proposed buyer EnergySolutions goes through, it would "combine the two most significant competitors for the disposal of low level radioactive waste (LLRW) available to commercial customers in 36 states, the District of Columbia and Puerto Rico," the Justice Department said in a statement announcing the civil antitrust lawsuit.

That merger would "deny commercial generators of LLRW – from universities and hospitals working on life-saving treatments to nuclear facilities producing 20 percent of the electricity in the United States – the benefits of vigorous competition that has led to significantly lower prices, better service and innovation in recent years."

"Since opening its LLRW disposal facility in 2012, Waste Control Specialists has provided EnergySolutions the only real competition it has ever faced," Assistant Attorney General Renata Hesse in the statement, which noted that "billions of dollars are set to be awarded in the coming years."

EnergySolutions said it would "vigorously defend" the pending acquisition, noting in a statement that "there are numerous disposal sites for LLRW waste operated by the competitors of the two companies."

A spokesman for Waste Control Specialists did not respond to an emailed request for comment.

In April, the company submitted an application to the Nuclear Regulatory Commission seeking to expand the radioactive waste dump it operates in Andrews County. It was seeking to store tens of thousands of metric tons of spent nuclear reactor fuel that is currently scattered across the country. (Federal policymakers have been trying to figure out what to do with the high-level radioactive waste for decades.)

The commission has requested additional information from the company in June that it has yet to provide. But the commission is still moving forward with its review and is seeking public comment on how the project could impact the environment, including endangered species, significant cultural resources and sensitive areas, along with increases in traffic and noise and dust from construction.

"We cannot proceed with the technical safety review until WCS adequately addresses our request for supplemental information, but we do have the information we need to begin the environmental scoping process now," said Mark Lombard, who heads the commission’s division of spent fuel management, in a statement this week. "WCS will bear the cost of staff time devoted to the environmental review, even if we are unable to docket the application in its current form."

Written comments can be submitted at www.regulations.gov; via email to WCS_CISF_EIS@nrc.gov; or by mail to Cindy Bladey, Office of Administration, Mail Stop: OWFN- 12 H08, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.

Read more of the Tribune’s related coverage:

  • Anti-nuclear groups seize on missing information in license application from Waste Control Specialists, which says it’s normal to add information to a complex, voluminous application.
  • The company operating a low-level nuclear waste dump in West Texas applied for a license to begin accepting highly radioactive spent nuclear fuel.
Fair Use Notice
This document contains copyrighted material whose use has not been specifically authorized by the copyright owner. SEED Coalition is making this article available in our efforts to advance understanding of ecological sustainability, human rights, economic democracy and social justice issues. We believe that this constitutes a "fair use" of the copyrighted material as provided for in section 107 of the US Copyright Law. If you wish to use this copyrighted material for purposes of your own that go beyond "fair use", you must obtain permission from the copyright owner.

WCS: Environmental study amid application process makes sense

Saturday, November 5, 2016

By Trevor Hawes
The Midland Reporter

Waste Control Specialists
Photo: Waste Control Specialists

A quartet of environmental groups last month wrote the U.S. Nuclear Regulatory Commission in an attempt to sway the agency to dismiss Waste Control Specialists’ pursuit of temporarily storing high-level nuclear waste in Andrews County, where it currently has a facility to permanently store low-level nuclear waste, according to a recent Houston Chronicle report.

The request came on the heels of the NRC’s decision to move forward with an environmental impact study for the proposed site despite not having fully reviewed WCS’ license application. These are years-long processes that company publicist Chuck McDonald said are not unheard of to be conducted simultaneously.

"It’s going to take years for the license application to work its way through the system, and it’s going to take multiple years for the EIS process to play out. Both give the public many opportunities to participate," he said. "The sooner we start the public participation, the better."

He said it also makes sense for the NRC to allow an environmental impact study during the application review because the commission won’t grant licensure unless an environmental impact study is passed; thus, the application itself requires the study.

Environmental groups, such as Public Citizen and Sierra Club, say Congress never approved of a private company storing high-level nuclear waste despite Energy Secretary Ernest Moniz’s testimony before Congress in September that the Department of Energy believes it can do so without congressional action.

The DOE in October issued a request for information from interested private entities. WCS and its competitor, Holtec, which is pursuing high-level nuclear waste storage in New Mexico across the state line from WCS’ facility, are expected to respond to the DOE’s request.

McDonald said the funding source might require Congress’ approval and cited two ways the DOE could pay for interim storage while the government finds a place for permanent geologic storage, which could take up to 40 years. One source comes from electric bill surcharges collected for waste disposal. This fund is at $40 billion, but there could be a catch.

"Congress originally stipulated that that fund could only be used for disposal, not interim storage," McDonald said.

The second source is through the $500 million taxpayers pay per year to utility companies after the utilities sued the DOE for failing to take high-level nuclear waste, which the agency is required by law to do.

"The DOE is saying it makes more sense to use that settlement money for funding storage because it’s coming from taxpayers’ pockets," McDonald said.
He said WCS is optimistic that its Andrews facility will ultimately be granted a contract for interim high-level nuclear waste storage despite federal projects like this moving "at glacial speed."

"We have two things going for us that no one else in the country can say," he said. "First, we have an operating low-level radioactive waste disposal facility with experienced employees that do this every day. The process for interim high-level nuclear waste storage is very similar.

"Second, we have a community that is very supportive of this and understands it after 20 years and has passed a resolution of support because they know this material can be handled safely and in an environmentally appropriate fashion, and it can be a source of revenue for the county. They’re willing to entertain other radioactive waste storage options. Not many places in the U.S. can bring that to the table for the federal government, and Andrews County is unique in that aspect."

McDonald said in a Reporter-Telegram report this summer that WCS is pursing interim storage of high-level nuclear waste because there is a growing need to store the waste safely in one place while the federal government decides where to store it permanently. The DOE is required by law to take waste from utilities, but it has failed to do so. The waste from fully decommissioned nuclear power plants is scattered across the nation, and the stockpiles are growing as more nuclear plants reach the end of their useful lives, about 40 years.

Last month, the Fort Calhoun plant in Kansas shut down. Seven more are expected to cease operations through 2025, according to the Energy Information Administration. In the next 25 years, McDonald said between 50 and 60 plants would come offline — all of them without a place to permanently store waste after the Obama administration ended pursuit of Yucca Mountain in Nevada as the waste’s home.

"They say if they restarted Yucca Mountain tomorrow, it would be about 25 years before they were ready to do permanent disposal there," McDonald said, adding that it’s best to move waste to a centralized location for safety and to give the space formerly occupied by nuclear plants back to communities.

Finding a home for nuclear waste nationally is the same process Texas had to go through, McDonald said.

"The state had an obligation to take waste from low-level radioactive waste generators. The state was unable to site a facility, so it passed legislation to contract with a private entity to meet its obligation. That’s the genesis for everything that’s WCS."

As for the environmental groups that want NRC to end WCS’ application process, "there’s a little bit of irony in the noise from those groups because they’re the ones who demand an opportunity to participate, but they are protesting the fact that this participation process has now begun," he said.

Like Trevor on Facebook and follow him on Twitter at @HowdyHawes.

Fair Use Notice
This document contains copyrighted material whose use has not been specifically authorized by the copyright owner. SEED Coalition is making this article available in our efforts to advance understanding of ecological sustainability, human rights, economic democracy and social justice issues. We believe that this constitutes a "fair use" of the copyrighted material as provided for in section 107 of the US Copyright Law. If you wish to use this copyrighted material for purposes of your own that go beyond "fair use", you must obtain permission from the copyright owner.

PG&E to close Diablo Canyon, California’s last nuclear power plant

June 21, 2016

Diablo Canyon
Pacific Gas & Electric’s Diablo Canyon plant near Avila Beach has California’s last operating nuclear reactors. (Michael Mariant / Associated Press)
By Ivan Penn and Samantha Masunaga
LA Times

One of California’s largest energy utilities took a bold step in the 21st century electricity revolution with an agreement to close its last operating nuclear plant and develop more solar, wind and other clean power technologies.

The decision announced Tuesday by Pacific Gas & Electric Co. to close its beleaguered Diablo Canyon nuclear plant within the next decade runs counter to the nuclear industry’s arguments that curbing carbon emissions and combating climate change require use of nuclear power, which generates the most electricity without harmful emissions.

Instead, PG&E joined with longtime adversaries such as the Friends of the Earth environmental group to craft a deal that will bring the company closer to the mandate that 50% of California’s electricity generation come from renewable energy sources by 2030.

PG&E’s agreement will close the book on the state’s history as a nuclear pioneer, but adds to its clean energy reputation. California already leads the nation by far in use of solar energy generated by rooftop panels and by sprawling power arrays in the desert.

"California is already a leader in curtailing greenhouse gases," said Peter Bradford, a former member of the U.S. Nuclear Regulatory Commission. "Now they’re saying they can go even further. That’s potentially a model for other situations."

Under the proposal, the Diablo Canyon Power Plant in San Luis Obispo County would be retired by PG&E after its current U.S. Nuclear Regulatory Commission operating licenses expire in November 2024 and August 2025.

The power produced by Diablo Canyon’s two nuclear reactors would be replaced with investment in a greenhouse-gas-free portfolio of energy efficiency, renewables and energy storage, PG&E said. The proposal is contingent on a number of regulatory actions, including approvals from the California Public Utilities Commission.

The Diablo Canyon nuclear plant, built against a seaside cliff near Avila Beach, provides 2,160 megawatts of electricity for Central and Northern California — enough to power more than 1.7 million homes.

Tuesday’s announcement comes after a long debate over the fate of the plant, which sits near several earthquake fault lines. The Hosgri Fault, located three miles from Diablo Canyon, was discovered in 1971, three years after construction of the plant began.

Diablo Canyon nuclear power plant will be shut down in 2025 after its operating licenses expire, owner Pacific Gas & Electric Co. has announced. Here’s a look at what will become of the plant, according to a recently revised plan by PG&E consultant TLG Services.
Calls to close Diablo Canyon escalated after a 2011 quake in Japan damaged two reactors at the Fukushima Daiichi nuclear power plant there, leading to dangerous radiation leaks. In the aftermath of that disaster, state and federal lawmakers called for immediate reviews of Diablo Canyon and the San Onofre nuclear plant in San Diego County, which was still in use.

The San Onofre plant was shut down for good in 2013 as a result of faulty equipment that led to a small release of radioactive steam and a heated regulatory battle over the plant’s license.

In documents submitted to the federal Nuclear Regulatory Commission as recently as last year, PG&E said Diablo Canyon can safely withstand earthquakes, tsunamis and flooding.

Daniel Hirsch, director of the program on Environmental and Nuclear Policy at UC Santa Cruz, said PG&E’s agreement was thoughtful.

"It is not simply a decision to phase out the plant, but to replace it with efficiency and renewables," he said. "So it is a very strong net gain for the environment."

As the state boosts its energy efficiency goals and plans for renewables, including solar and wind power, Hirsch said, Diablo Canyon is "getting in the way."

PG&E Chief Executive Tony Earley acknowledged the changing landscape in California, noting that energy efficiency, renewables and storage are "central to the state’s energy policy."

"As we make this transition, Diablo Canyon’s full output will no longer be required," he said. That eventually would make the nuclear plant too expensive to operate, Earley said during a conference call with reporters.

Diablo Canyon LA Times archives

Hirsch tempered his approval with caution, saying that as long as the plant remains in operation, safety risks remain.

"Diablo really does pose a clear and present danger," he said. "If we had an earthquake larger than the plant was designed for, you could have a Fukushima-type event that could devastate a large part of California."

State senate leader Kevin de León (D-Los Angeles) echoed Hirsch by saying nuclear energy is "inherently risky, and the Diablo Canyon Power Plant is vulnerable to damage from natural disasters that could threaten the well-being of millions of Californians. This transition will make our energy sources less volatile, more cost-effective, and benefit the air we breathe."

In the mid-2000s, the nation’s utilities had anticipated a nuclear renaissance that would usher in a new age of centralized power plants. Power companies submitted proposals to the U.S. Nuclear Regulatory Commission for 31 new reactors. President George W. Bush pushed federal loan guarantees to hasten nuclear plant construction.

However, instead of a renaissance, the nuclear industry began to unravel.

Duke Energy announced in February 2013 that it would close the Crystal River, Fla., nuclear plant after a steam generator replacement project led to cracks in the concrete reactor containment building. The plant became too costly to fix.

In May 2013, Dominion Resources Inc., permanently shut down the Kewaunee nuclear plant in Wisconsin after the power company said it was no longer affordable to operate the facility.

A month later, Southern California Edison permanently closed the San Onofre plant after the determining that fixing the new but faulty steam generators would prove too expensive.

California's Nuclear History chart

Perhaps the biggest problem for the nuclear industry was the vast amount of natural gas that became available in the United States because of fracking.

Natural gas plants now are far cheaper to build and operate than a nuclear plant. A natural gas facility runs at about 8 or 9 cents a kilowatt hour compared with twice that much for a nuclear plant.

And the push for renewable energy has turned attention to solar and wind power to help reduce emissions and combat human-caused climate change.

"The unraveling of the renaissance was not a surprise to anyone who understood the workings of the power markets," said Bradford, the former U.S. Nuclear Regulatory Commission member. He serves as an expert witness in legal proceedings across the nation.

Bradford said PG&E’s plan for Diablo Canyon shows the flaws in arguments by the nuclear industry that a clean-energy network requires nuclear.

"It’s a very tough day for people who have been advocating for massive nuclear subsidies," Bradford said.

Even after Diablo Canyon closes, Southern California will still get a small percentage of its electricity from Arizona’s Palo Verde nuclear plant. Among the owners of the 4,000 megawatt nuclear plant in the Arizona desert are Southern California Edison, the Los Angeles Department of Water and Power and the Southern California Public Power Authority, whose members include municipal power companies supplying Glendale, Pasadena, Burbank and Anaheim.

The impending closure of Diablo Canyon would leave just one nuclear plant on the West Coast, the Columbia Generating Station, about 200 miles outside of Seattle.

To craft Tuesday’s proposal, PG&E worked with the International Brotherhood of Electrical Workers Local 1245, the Coalition of California Utility Employees, the Natural Resources Defense Council, Environment California, Friends of the Earth and the Alliance for Nuclear Responsibility.

ivan.penn(at)latimes.com
samantha.masunaga(at)latimes.com

West Texas Site Applies for Nuke Waste License

April 28, 2016

by Marisa Endicott Medill News Service
via The Texas Tribune

WASHINGTON — A West Texas toxic waste storage facility is seeking a license to accept and store spent nuclear reactor fuel, much of it highly radioactive.

Waste Control Specialists, which operates a low-level nuclear waste dump in Andrews County, announced Thursday that it has applied for the license to build and maintain a temporary storage site for the spent fuel.

“We think we’ve got a great site, we’ve got consent with the local community, we think the license application is really good," said Rod Baltzer, the company’s president and CEO in an interview after the announcement at the National Press Club.

The company said it is partnering with AREVA Inc. and NAC International Inc., longtime industry leaders in nuclear waste engineering and transportation. The group hopes to start construction by 2019 after a standard three-year review by the Nuclear Regulatory Commission. If the NRC signs off on the application, the facility could begin accepting used nuclear fuel by 2021.

The proposal faces some public opposition, and possible complications from uncertain legal procedures and support on Capitol Hill.

Political and industry leaders have spent decades unsuccessfully seeking a permanent storage facility for the nation’s roughly 70,000 metric tons of accumulated spent fuel and radioactive byproducts from nuclear reactors. Power plants have been forced to store the waste despite a promise by the government to find an alternative location.

The Yucca Mountain site in Nevada was long considered the most viable option, but that state’s congressional delegation blocked the plan. WCS would serve as an interim solution while the hunt continues for a permanent site.

“We’ve got a unique environment and a unique state, and I think they understand the risks and the technical challenges," Baltzer explained. “But they also know that with the proper regulatory oversight and the proper technology that you can overcome those."

WCS currently oversees a 14,000-acre low-level waste disposal facility. The application seeks a 40-year license to take in up to 40,000 metric tons of higher level waste in eight phases, with the possibility for 20-year renewals going forward. The temporary storage facility would occupy 320 acres, or 2.2 percent of the facility’s property, according to the proposal.

“We are prepared for – I’ll call it – the long haul," Baltzer said. “We’ve told our community this could be 60 to 100 years."

That raises a red flag for opponents like Diane D’Arrigo, a project director at the non-profit Nuclear Information and Resource Service. “It will give the illusion of a solution," she said.

Critics say transporting highly radioactive material through densely populated areas will pose risks to residents of Texas and nearby New Mexico, and other regions of the country. Spent nuclear fuel from power plants could be vulnerable in transit to accidents or attacks, exposing people and land to long-term radioactive poisoning, opponents of the Texas project say.

The SEED Coalition and the activist group Public Citizen highlighted these and other concerns in a statement that quoted the Dallas County Commissioner Theresa Daniel and Bexar County Commissioner Tommy Calvert, among others.

During the news conference in Washington, Mike McMahon, AREVA Inc.’s vice president, said the firm has a long track record of hauling fuel without incident. Transportation of nuclear transportation is safe, McMahon insisted.

“We transport tremendous amounts of material every day," he said. “The Navy transports nuclear fuel on a routine basis."

Detractors remain unconvinced.

“They may talk about the record, but the record is nothing compared to what we’re going to be unleashing," D’Arrigo said in an interview following the announcement. “If they approve this site, we will have literally thousands, tens of thousands of shipments over the next few decades on our roads and rails."

Another challenge for the Texas waste facility will be navigating legal and Congressional hurdles. For the project to go forward, the Department of Energy would have to assume the title to – and liability for – the spent nuclear fuel stored at the site, but it is unclear whether the DOE can take such action on its own or needs Congressional approval.

Legislation introduced last September by Rep. Mike Conaway, R-Texas, of Andrews, and another bill proposed in March by Rep. Mick Mulvaney, R-S.C., would authorize the government to send spent nuclear fuel to a temporary site. But neither measure has made it past the initial introductory step.

"The biggest x-factor for us is the contractual matters, and can and when DOE would take title to it and what that process looks like," Baltzer said.